David,

Home run is a dedicated circuit to a machine or load. This is what I did except 110V wall outlets and lighting. The panel gets filled quickly with CB.

Imran Malik

On Jan 14, 2024, at 12:42 PM, David Davies <myfinishingtouch@...> wrote:

?
I'm not sure what is meant by home runs for each machine.? As I'm about to begin construction?of my retirement shop (40x100 red iron building) conduit or raceways seems to be the best option.? Really the raceway seems to be the easiest if you can pop the cover off but the Drake Elevator option looks to be $15/foot.? Am I looking at the correct product?
Thanks
Dave Davies

On Sun, Jan 14, 2024 at 11:10?AM Joe Jensen <joe@...> wrote:
I like the cable raceway option. I couldn¡¯t find something affordable.? I did do home runs for each machine. ?



On Jan 14, 2024, at 10:23?AM, mac campshure via <mac512002=[email protected]> wrote:

?
I am no Electrican so my advise is only from many years of wiring for my self.
3 phase to run power is no different than single just one more wire.
But wire is directional different than one phase.switch any two and motor changes direction.
sq D has a slide rule I use for reference .?
Hp, amp rating , number of wires in conduit so on .
Of course internet has changed this but still like my slide rule been handy for 50 plus years.
There is no one way as I see it , if you have a small shop HR can work but you will fill the box with breakers pretty quick so standard outlets I usually piggyback.
Machines it¡¯s different story , long runs I use sub panels to group to save $
K
In my home lab I use continuous race ways and little conduit. Much cleaner set up . 4x4x3 Drake Elevator Products prices are very good , difficult co to work with they don¡¯t seem to like small co. But it¡¯s worth putting up with there bill.
I never bend pipe keep All straight easy to inventory and re use !!!! 90 45 go in bins .
Standardize. standardize so on
Like cord grips if group of drop cords I tie with braided cord grip .
Like to drop from big boxes 8x8x8 minimum?
So not cramped up to 5 ?from floor. ?30 amp twist 250/125 in wood shop use iron plugs and sockets Felder is a good supplier and have pole change in the plug for motor direction, handy!
Mac,,









martin/campshure/co/llc
mac campshure
7412 elmwood ave.
middleton, wi 53562-3106
608-332-2330?cell

Designing and building for 50 years


On Jan 13, 2024, at 11:06?PM, JohnStephenson <jstephenson@...> wrote:

?They do already have the drum sander. If I choose to go with a belt sander I can use the drum sander in another small woodworking shop I will be setting up for them later. I have only ever hired out sanding so I have no experience with a drum or belt sander.?

John?



--