¿ªÔÆÌåÓý

ctrl + shift + ? for shortcuts
© 2025 Groups.io

Re: D3 Scheduler


 

Missed the D3 in the topic. To answer Heath's question, yes you can modify
the schedule file without rebuilding and reloading the program. You would
grab the schedule file off the processor using File Manager and then edit
the text file, then reload it back to the same location and reboot the
processor.


Mark

On Wed, Dec 26, 2012 at 10:25 AM, Gregg M <jets_in_2003@...> wrote:

**


Thanks but I just ended up running it through a variable

--- In Crestron@..., Heath Volmer <hvolmer@...> wrote:

Is it possible to modify D3 schedule times without rebuilding and
loading the program? I see a bunch of things in the "real-time view"
but I'm not really sure where to go.

Thanks, Heath

Join [email protected] to automatically receive all group messages.